Liquidated Damages under Section 74 of the Contract Act: Does a Claimant Still Have to Prove Loss?
Commercial contracts routinely include a liquidated damages clause that fixes a sum payable for breach, such as a specified amount for each week of delay or a percentage of the con
Arbitration Timing Guidelines: Insights from Delhi High Court’s Interpretation of the Arbitration and Conciliation Act, 1996
In a detailed judgment, the Delhi High Court has elucidated on the precise timing required for invoking arbitration under the Arbitration Timing Guidelines set forth by the Arbitra