Arbitral award is not a decree under Section 2(2) of CPC, therefore, objection filed under Section 47 of CPC is not maintainable
Case Analysis: India Oil Corporation Ltd. and Another Vs. The Commercial Court and Another

Introduction
The jurisprudential distinction between arbitral awards and court decrees represents a fundamental aspect of contemporary arbitration law in India. The landmark case of India Oil Corporation Ltd. and Another v. The Commercial Court and Another, decided by the Allahabad High Court, provides critical clarity on this legal framework, establishing definitively that an arbitral award is not a decree under Section 2(2) of the Code of Civil Procedure, 1908 (CPC) [1]. This principle has far-reaching implications for the enforcement of arbitration awards and the scope of objections that may be raised during execution proceedings.
The Allahabad High Court’s decision, delivered by Justice Neeraj Tiwari on September 6, 2023, addressed several interconnected legal questions that have significant ramifications for arbitration practice in India. The court examined whether arbitration proceedings commenced under the old Arbitration Act, 1940, could continue under the provisions of the Arbitration and Conciliation Act, 1996, whether arbitral awards constitute decrees under the CPC, and crucially, whether objections under Section 47 of the CPC are maintainable in execution proceedings for arbitral awards.
Factual Background and Procedural History
The dispute in India Oil Corporation Ltd. originated from a contractual relationship established in 1989 between the parties. On July 1, 1989, Original Suit No. 436 of 1989 was filed for the appointment of an arbitrator under the Arbitration Act, 1940. The Honorable Mr. Justice R.P. Singh (Retired) was subsequently appointed as the arbitrator on August 12, 1991. However, due to intervening litigation, the actual arbitration proceedings could only commence in 2001, by which time the Arbitration and Conciliation Act, 1996 had come into effect.
The arbitrator, recognizing the changed legal landscape, passed an order in 2002 directing that proceedings would continue under the provisions of the Arbitration and Conciliation Act, 1996. The arbitral award was eventually passed on April 27, 2005, directing the respondent to pay ₹7,79,871 to the petitioner. This award was subsequently sent to the Additional District Judge-IX, Civil Court, Varanasi for enforcement.
The execution proceedings were initiated through Execution Application No. 21 of 2012, later renumbered as Execution Application No. 24 of 2020. The petitioner raised objections under Section 47 of the CPC, which were rejected by order dated August 8, 2022. This rejection led to the filing of the present petition under Article 227 of the Constitution of India, challenging the maintainability of such objections.
Transitional Applicability: From the 1940 Act to the 1996 Act
The first significant legal issue addressed by the Allahabad High Court concerned the transitional provisions governing arbitration proceedings that commenced under the old Arbitration Act, 1940, but continued under the Arbitration and Conciliation Act, 1996. Section 85(2)(a) of the 1996 Act provides that the old Act shall cease to have effect except in respect of arbitral proceedings that commenced before the new Act came into force.
The court relied heavily on the Supreme Court’s decision in Thyssen Stahlunion GmbH v. Steel Authority of India Ltd., which established that parties can agree to the applicability of the new Act even for agreements made before its enactment [2]. The Allahabad High Court observed that the arbitration clause in the original agreement explicitly provided for applicability not only of the old Act but also of “all statutory re-enactments and modification thereof and rules framed thereunder.”
This interpretation reflects a pragmatic approach to transitional provisions in arbitration law. The court emphasized that there was no requirement for a fresh agreement to comply with Section 85(2)(a) of the 1996 Act, as the original arbitration clause was sufficiently broad to encompass subsequent legislative enactments. This finding has significant implications for numerous arbitration proceedings that originated under the 1940 Act but continued under the current statutory framework.
Definitional Analysis: Arbitral Awards versus Court Decrees
The central legal question addressed by the court concerned the fundamental nature of arbitral awards and their relationship to court decrees as defined under Section 2(2) of the CPC. Section 2(2) of the CPC defines a decree as “the formal expression of an adjudication which, so far as regards the court expressing it, conclusively determines the rights of the parties with regard to all or any of the matters in controversy in the suit.”
The Supreme Court’s landmark judgment in Paramjeet Singh Patheja v. ICDS Ltd. provides the authoritative pronouncement on this issue [3]. In paragraph 29 of that judgment, the Supreme Court categorically held that “it is obvious that an arbitrator is not a Court, an arbitration is not an adjudication and, therefore, arbitral award is not a decree.” This clear judicial reasoning reinforces the legal position that an arbitral award is not a decree within the meaning of Section 2(2) of the CPC. The court further observed in paragraph 31 that the words “decision” and “Civil Court” in the definition of decree “unambiguously rule out an award by arbitrators to be a decree.”
The Allahabad High Court in India Oil Corporation Ltd. extensively analyzed these definitional distinctions. The court observed that the use of terms “adjudication” and “suit” in Section 2(2) clearly indicates that only courts can pass decrees in suits commenced by plaint, adjudicating disputes between parties through judgments pronounced by courts. An arbitral award, by contrast, represents the decision of an arbitrator appointed by parties or by a court, but it does not constitute a formal expression of adjudication by a court.
Furthermore, the court distinguished that an arbitral award is not a decree because it does not conclusively determine the rights of parties in the same manner as a court decree. Arbitral awards remain subject to challenge under Section 34 of the Arbitration and Conciliation Act, 1996, whereas court decrees, once they attain finality, cannot be challenged on the same grounds. Additionally, arbitral awards address only those matters referred to arbitration by the parties, unlike court decrees which may deal with all matters in controversy in a suit.
The Enforcement Mechanism Under Section 36
Section 36 of the Arbitration and Conciliation Act, 1996, establishes the framework for enforcement of arbitral awards. Section 36(1) provides that where the time for making an application to set aside the arbitral award under Section 34 has expired, such award shall be enforced in accordance with the provisions of the CPC “in the same manner as if it were a decree of the court” [4].
The phrase “as if it were a decree” creates what courts have termed a “legal fiction” for the limited purpose of enforcement. This legal fiction does not transform the arbitral award into an actual decree but merely provides that the enforcement mechanisms available for court decrees should be made available for arbitral awards. The Supreme Court in Paramjeet Singh Patheja clarified that this provision enables arbitral awards to be executed invoking Section 36 along with the provisions of the CPC, but the award itself does not become a decree under Section 2(2) of the CPC.
The Allahabad High Court in India Oil Corporation Ltd. emphasized this distinction between enforcement and actual status. The court observed that an arbitral award is not a decree in itself. Rather, Section 36 of the Arbitration and Conciliation Act, 1996 provides for its enforcement in the same manner as a decree. Enforcement means giving legal sanction or recognition to an award by declaring it binding and conclusive on the parties, whereas execution involves taking steps to compel compliance by the judgment debtor.
The enforcement provisions under Section 36 reflect the legislature’s intent to provide arbitral awards with the same practical effectiveness as court decrees while maintaining their distinct legal character. This approach ensures that successful parties in arbitration proceedings can secure the benefits of their awards without facing additional procedural hurdles, while preserving the integrity of the arbitration process.
The Non-Maintainability of Section 47 CPC Objections
Section 47 of the CPC governs objections in execution proceedings and provides that “all questions arising between the parties to a suit in which a decree has been passed relating to its execution shall be determined by executing court.” The scope of Section 47 is limited to questions concerning the execution, discharge, or satisfaction of a decree and does not extend to substantive challenges to the decree itself.
The Allahabad High Court’s decision in India Oil Corporation Ltd. definitively established that since arbitral award is not a decree under Section 2(2) of the CPC, objections under Section 47 cannot be maintained in execution proceedings for arbitral awards. This conclusion flows logically from the fundamental distinction between awards and decrees established by the Supreme Court in Paramjeet Singh Patheja.
The court relied on several precedents to support this conclusion, including its earlier decision in Larsen & Tubro Limited v. Maharaji Educational Trust and the subsequent case of M/s Chopra Fabricators and Manufacturers Pvt. Ltd. v. Bharat Pumps and Compressors Ltd [5]. These decisions consistently held that once the stage of Section 34 proceedings is over, questions that were raised or could have been raised at that stage cannot be permitted to be raised again through objections under Section 47 of the CPC.
The rationale for this position extends beyond mere procedural considerations. The Arbitration and Conciliation Act, 1996, provides a specific and comprehensive framework for challenging arbitral awards through Section 34. This section allows parties to raise objections on grounds including jurisdictional issues, procedural irregularities, and substantive challenges to the award. Permitting additional challenges through Section 47 of the CPC would effectively circumvent this carefully structured mechanism and undermine the finality that the arbitration process is designed to achieve.
Judicial Precedents and Consistent Application
The principle established in India Oil Corporation Ltd. has been consistently applied by Indian courts in subsequent decisions. The Supreme Court’s decision in Paramjeet Singh Patheja remains the foundational authority on the distinction between arbitral awards and court decrees. This decision has been cited approvingly by numerous High Courts across India, demonstrating the settled nature of this legal principle.
In the recent case of State of U.P. and Ors. v. Shri Raj Veer Singh, the Allahabad High Court imposed costs of ₹5 lakhs on the State of Uttar Pradesh for raising frivolous objections under Section 47 of the CPC in execution proceedings [6]. Justice Shekhar B. Saraf observed that such delay tactics “serve to perpetuate injustice by denying parties their rightful entitlements” and emphasized the need for courts to exercise vigilance in identifying and dismissing frivolous objections.
The Delhi High Court has also consistently applied this principle. In Hindustan Zinc Ltd. v. National Research Development Corporation, the court held that since objections under Section 47 of the CPC are not available in proceedings under Section 36 of the Arbitration Act, challenges to arbitral awards on their merits cannot be permitted during enforcement proceedings [7].
Practical Implications for Arbitration Practice
The legal principle established by these decisions has significant practical implications for arbitration practitioners and parties to arbitration agreements. Parties seeking to challenge arbitral awards must do so within the framework provided by the Arbitration and Conciliation Act, 1996, primarily through applications under Section 34. The time limitation of three months for filing such applications, extendable by a maximum of thirty days for sufficient cause, emphasizes the importance of prompt action.
The non-maintainability of Section 47 objections in execution proceedings serves several important policy objectives. First, it promotes the finality of arbitral awards, which is essential for the effective functioning of arbitration as an alternative dispute resolution mechanism. Second, it prevents dilatory tactics by unsuccessful parties who might otherwise seek to prolong proceedings through successive challenges. Third, it maintains the integrity of the arbitration process by ensuring that challenges follow the specific procedures established by the governing statute.
For legal practitioners, these decisions underscore the importance of comprehensive preparation during Section 34 proceedings. All potential challenges to an arbitral award must be raised at this stage, as subsequent opportunities for challenge are extremely limited. This requirement places a premium on thorough analysis of arbitral awards and careful preparation of challenge applications.
The Broader Context of Arbitration Law Reform
The legal principles established in India Oil Corporation Ltd. and related cases must be understood within the broader context of arbitration law reform in India. The Arbitration and Conciliation Act, 1996, was enacted to modernize India’s arbitration framework and align it with international best practices. The Act was subsequently amended in 2015, 2019, and 2021 to address various practical challenges and further strengthen the arbitration ecosystem.
The emphasis on limiting challenges to arbitral awards reflects a deliberate policy choice to promote arbitration as an efficient alternative to traditional litigation. The principle of minimal judicial intervention, enshrined in Section 5 of the Act, requires courts to refrain from unnecessary interference in arbitral proceedings. The restriction on Section 47 objections in execution proceedings is consistent with this overarching philosophy.
The Supreme Court’s approach in cases like Paramjeet Singh Patheja reflects a careful balance between ensuring the enforceability of arbitral awards and preserving essential safeguards against manifestly erroneous or fraudulent awards. The Section 34 mechanism provides adequate protection for parties while maintaining the efficiency that makes arbitration attractive to commercial parties.
Future Considerations and Recommendations
The settled legal position regarding the non-maintainability of Section 47 objections in execution of arbitral awards represents an important step toward strengthening India’s arbitration framework. However, certain considerations merit attention for future development of this area of law.
First, there is a need for greater awareness among legal practitioners about the limited scope for challenging arbitral awards. Educational initiatives and professional development programs should emphasize the importance of thorough preparation during Section 34 proceedings and the finality of arbitral awards once that stage is concluded.
Second, courts should continue to impose appropriate costs on parties who raise frivolous objections during execution proceedings. The decision in State of U.P. v. Shri Raj Veer Singh, imposing costs of ₹5 lakhs, demonstrates the courts’ willingness to deter dilatory tactics through financial consequences.
Third, the development of specialized commercial courts and arbitration-specific procedures may further enhance the efficiency of award enforcement. The Commercial Courts Act, 2015, has already made significant contributions in this regard, and continued refinement of these mechanisms will benefit the arbitration ecosystem.
Conclusion
The Allahabad High Court’s decision in India Oil Corporation Ltd. and Another v. The Commercial Court and Another represents a significant contribution to the development of arbitration jurisprudence in India. By definitively establishing that arbitral awards are not decrees under Section 2(2) of the CPC and that objections under Section 47 of the CPC are not maintainable in execution proceedings, the court has provided important clarity on fundamental questions of arbitration law.
The decision builds upon the foundational principles established by the Supreme Court in Paramjeet Singh Patheja v. ICDS Ltd. and demonstrates the consistent application of these principles across Indian courts. The emphasis on the distinct nature of arbitral awards, the limited scope of legal fiction created by Section 36 of the Arbitration and Conciliation Act, and the comprehensive nature of the Section 34 mechanism reflects a mature understanding of arbitration law.
For practitioners and parties involved in arbitration proceedings, these decisions underscore the importance of understanding the specific procedures and limitations governing challenges to arbitral awards. The finality accorded to arbitral awards, subject only to the limited grounds specified in Section 34, serves the broader objective of promoting arbitration as an efficient and effective mechanism for commercial dispute resolution.
The legal framework established by these decisions contributes to India’s evolving reputation as an arbitration-friendly jurisdiction. By limiting opportunities for dilatory challenges and emphasizing the binding nature of arbitral awards, Indian courts are sending a clear message about their commitment to supporting the arbitration process and encouraging its use by commercial parties.
As India continues to develop its arbitration ecosystem, the principles established in cases like India Oil Corporation Ltd. will serve as important guideposts for future developments. The balance struck between enforceability and essential safeguards provides a solid foundation for the continued growth and refinement of arbitration practice in India.
References
[2] Thyssen Stahlunion GmbH v. Steel Authority of India Ltd., (1999) 9 SCC 334
[3] Paramjeet Singh Patheja v. ICDS Ltd., AIR 2007 SC 168, (2006) 13 SCC 322
[4] Section 36, Arbitration and Conciliation Act, 1996, available at: https://www.indiacode.nic.in/show-data?actid=AC_CEN_3_46_00004_199626_1517807323919&orderno=40
[5] Larsen & Tubro Limited v. Maharaji Educational Trust, 2010 SCC Online AII 1866,
[6] State of U.P. and Ors. v. Shri Raj Veer Singh, Allahabad High Court (2024)
[7] Hindustan Zinc Ltd. v. National Research Development Corporation, 2023 SCC OnLine Del 330
[8] Commercial Courts Act, 2015, available at: https://nalsa.gov.in/the-commercial-courts-acts-rules/the-commercial-courts-acts
[9] Code of Civil Procedure, 1908, Section 2(2), available at: https://indiankanoon.org/doc/1331755/
Authorized by Rutvik Desai
Whatsapp
